Deprecated: Methods with the same name as their class will not be constructors in a future version of PHP; ctools_context has a deprecated constructor in /home/lps/public_html/sites/all/modules/contrib/ctools/includes/context.inc on line 30

Deprecated: Methods with the same name as their class will not be constructors in a future version of PHP; ctools_context_required has a deprecated constructor in /home/lps/public_html/sites/all/modules/contrib/ctools/includes/context.inc on line 93

Deprecated: Methods with the same name as their class will not be constructors in a future version of PHP; ctools_context_optional has a deprecated constructor in /home/lps/public_html/sites/all/modules/contrib/ctools/includes/context.inc on line 205

Deprecated: Methods with the same name as their class will not be constructors in a future version of PHP; panels_cache_object has a deprecated constructor in /home/lps/public_html/sites/all/modules/contrib/panels/includes/plugins.inc on line 117
Little Raven Elementary | Littleton Public Schools

Little Raven Elementary

Thank you, Littleton Public Schools voters! Through your support of a $298M bond and the district's receipt of premium bond dollars, LPS is able to build a third elementary school as part of the 2018 bond program. During a special meeting Tuesday, March 30, 2021, the Board of Education took action on the location for this new elementary school for the combined East and Ralph Moody Elementary communities. In a 5-0 vote, the Board chose the Ralph Moody campus as the site of the new school. The Long Range Planning Committee, which had been charged by the Board toe vet and validate administration's recommendation to build on the Ralph Moody campus, agreed with administration's recommendation after taking into consideration all of the data collected over the past three years related to facilities and boundaries as well as parent, staff, and community feedback.

The Board of Education named the new school at their meeting on December 9, 2021. Little Raven Elementary School provides the appropriate space for small- and large-group instruction, creativity, and innovation. It includes new playgrounds, playing fields, and parking to serve the neighborhood. Little Raven Elementary opened for students in the fall of 2023.

Updates

(September 2024) Kitchen serving line will be installed over long weekend in October.

(August 2024) Summer work is complete; kitchen serving line will take place in October.

(June 2024) Cafeteria floor replacement is complete. Turf field work will begin mid-June. Kitchen serving line updates will be completed this summer.

(May 2024) Cafeteria flooring replacement, serving line installation, and turf field rework scheduled for Summer 2024. Intersection/bump out was completed over spring break.

(March 2024) Summer work will include cafetorium flooring replacement, serving line, and some turf field work. Obtained final Certificate of Occupancy.

(January 2024) Working on final Certificate of Occupancy. Cafeteria flooring is being replaced, as well as some work to the serving line.

(November 2023) Punch list and warranty work is taking place over Thanksgiving break.

(September 2023) Punch list for building interior is ongoing. Playgrounds are open; field turf is in progress. 

(August 2023) Staff are in the building! Furniture installation is complete. Teacher materials have been moved from East and Twain buildings. School will open with play pads, main playground, and kindergarten play area (play areas are largely located between wings behind the building). Fields will not be complete at start of school but will be done as soon as possible this fall. All egress to the school will be complete by start of school.

(May 2023) Site work is ongoing with parking lot and playgrounds. Interior wings are nearing completion and punch list work has started. 

(April 2023) Water line work is about halfway complete. Interior wings are nearing completion, and punch list work has started. On schedule for substantial completion in early July.

(March 2023) Mechanical equipment has been delivered. Rooftop HVAC units have been installed. Wood ceilings being installed. Exterior metal siding, masonry, roofing metal work will be completed in the next 3 weeks; window glazing will follow.

(December 2022) Exterior skin is underway. Interior work is ongoing. Roofing is progressing but moving slowly--this is not impacting the schedule. Denver Water and the issues with procuring 3-inch ductile iron pipe for service connection could potentially impact schedule, but Jacobs is working with Denver Water to find a solution.

(November 2022) MEP, masonry, exterior skin framing, interior wall work is ongoing. Roofing is complete for some wings (approximately half of the building). Drywall installation and painting is in progress where the roof has been completed. Denver Water is requiring a 3-inch ductile iron pipe for service connection, but ductile iron pipe is currently unavailable in the United States, so currently alternative options are being considered.

(October 2022) Mechanical, electrical, plumbing is ongoing. Masonry and skin framing is underway. Interior wall work is underway and ongoing, and the complete demolition of old Moody building is scheduled to be completed by the end of this month. 

(August 2022) The steel structure is under construction, along with interior framing, concrete on deck, utility rough-ins, and work is on schedule! Abatement is being done in phases, and the demolition of the old Ralph Moody building is scheduled to start mid-August with a end-of-September plan for completion. Work is underway with the City of Littleton on the installation of a new traffic light.

(June 2022) Concrete flatwork and utility work is ongoing. Abatement is underway and making good progress, and demolition of the northeast wing is scheduled to begin this month. Masonry is scheduled to begin towards the end of this month. Work with the City of Littleton on installation of a new traffic light is underway.

(April 2022) The contractor has mobilized on site and is working on grading and foundations on the east side of the property. Coordination of the move from the old Moody building to Twain for the 2022–2023 school year is underway.

(March 2022) Groundbreaking ceremony is being planned. Final pricing is being negotiated, but pricing is higher than anticipated due to supply chain issues and cost escalations. Contractor is on site and mobilization is underway. Coordination on moving to the Twain building is ongoing, and moving is anticipated to happen in late May after the end of the school year.

(February 2022) Bidding phase is underway to arrive at a Guaranteed Maximum Price (GMP). At this point, playgrounds may be delayed due to abatement work; however, the parking lot and building will be ready for the start of school in August 2023. Site coordination is underway between bond managers and school administration to potentialy mobilize the site by the end of February.

(November 2021) Site mobilization is anticipated in late February. Parking lot and building are scheduled to open in August 2023, but there may be some delays to playground equipment. The plan for moving Moody students and programs into the Twain building for the next school year is underway.

(November 2021) Design is progressing, and early pricing packages are currently being bid. Early procurement for construction materials has started.

(Fall 2021) The new elementary school on the Ralph Moody campus is in the very early phases of design. More information will be communicated as the project progresses.

Conceptual Drawing of Little Raven Elementary School

This is a conceptual plan that was presented to the Board of Education as a possibility for where the new elementary school could be located on the Ralph Moody campus. It is not the final design.